Why would the City invite neighbors to meet a construction team for a reservoir the City doesn't expect to start building until spring 2028? On Wednesday, September 30, the Vic Trace Reservoir Replacement Project team set up next to the reservoir driveway at 1633 La Coronilla Drive, offered refreshments, and introduced the firm that will oversee the work. That same week, crews were working overnight a few blocks away at Meigs Road and Cliff Drive on a different project.
When you see cones on the Mesa, it's easy to assume they all belong to one big dig. They don't. The City has set up three separate projects to run one after another, and each one waits for the one before it. The loudest, longest and most expensive of the three comes last. That gives Mesa homeowners about a year and a half of notice, plus several public decision points that haven't happened yet.
Who was actually at 1633 La Coronilla
The firm introduced on September 30 was Tynan Group. It's the project's construction management team, not the company that will build the reservoir. The City describes Tynan Group as a Santa Barbara-based firm with 35 years of experience. It's partnering with Black & Veatch, a global engineering firm, and together the two firms will help "coordinate between the contractor, City project staff, and the community." The City's September 15 Council agenda recommended a Tynan contract of $1,257,420 for construction management during the design phase. "During design" is the key phrase. The City's June 2026 FAQ still lists design and environmental review as running through spring 2027.
The City calls the meet-and-greet its quarterly event. It's an early introduction, not a sign that work starts next week.
Here's how the three projects line up, based on the City's most recent published timing as of early October 2026:
| Project | Where it touches the Mesa | When | What it means day to day |
|---|---|---|---|
| Cliff Drive Watermain Replacement | Meigs Road and Cliff Drive intersection | Night work from mid-August, expected done by early November 2026 | 8 p.m. to 7 a.m. crews, traffic control, possible delays |
| Cliff Drive Vision Zero | Cliff Drive from Arroyo Burro County Park to Castillo Street | Out to bid in fall 2026 (planned); construction expected to start spring 2027 | Construction phasing to be shared once a contractor is selected |
| Vic Trace Reservoir Replacement | 1633 La Coronilla Drive, plus pipelines on surrounding streets | Preconstruction winter 2027 to spring 2028; construction spring 2028 to 2031 | Weekday work hours, haul trucks, parking restrictions starting in 2028 |
The noise you hear this fall comes from the watermain project
The overnight work at Meigs and Cliff belongs to the Cliff Drive Watermain Replacement Project. The City's August 3 notice said crews would work 8 p.m. to 7 a.m. "to reduce impacts to businesses and daytime traffic." It asked drivers to expect noise, temporary traffic control and possible delays, and to use another route when possible. Access for residents and emergency vehicles stays open.
The City's older project page still says the watermain work "will be completed in summer 2026." The August notice gives a later date for one piece of that work. The night work at Meigs and Cliff is expected to wrap up by early November, weather and field conditions permitting. As of today, that's roughly a month away. The City hasn't published a completion date for the watermain project as a whole.
The watermain's finish matters beyond the intersection, because the City has scheduled Vision Zero construction to follow it.
Spring 2027 is Cliff Drive's turn
The City's March 24 update says the Cliff Drive Vision Zero Project's design is nearly finished. The City planned to advertise the project for construction bids this fall, with construction "anticipated to begin in spring 2027 following completion of the Cliff Drive Watermain Replacement Project." We couldn't find a public notice confirming the bids have gone out yet. For now, fall 2026 is the plan, not a confirmed milestone.
The project is large. It includes a three-mile separated path from Arroyo Burro County Park to Castillo Street, upgraded crossings, and a wider sidewalk on Loma Alta. The Mesa Neighborhood Association lists its cost at $34 million. The City says the next round of community meetings will focus on construction phasing once a contractor is selected. That means the block-by-block schedule for Cliff Drive doesn't exist yet in any published form.
The Vision Zero and Vic Trace teams are planning around each other. The City's Vic Trace FAQ says staff from both teams "continue to work closely with one another" so that schedules and traffic impacts "minimize compounding impacts for the surrounding community." That coordination is the reason the projects run one after another.
2028, and why Dolores Drive matters
The Vic Trace Reservoir was built in 1956. It's a partially buried, 10-million-gallon concrete tank and the City's largest single reservoir, serving nearly 60,000 people, about 70% of the city. It's named for Victor "Vic" Trace, the City's water superintendent from 1900 to 1934. The plan replaces it with two buried tanks, so one can stay in service while the other is being repaired. The City's current cost estimate is $130 million. Funding options include low-interest state Drinking Water Revolving Fund loans, grants and possible bond measures.
The timing has shifted later over the past year. In February, KEYT reported Public Works staff saying construction would happen between 2028 and 2030. The City's June 2026 FAQ now says spring 2028 to 2031. According to a Santa Barbara Civic Platform summary of the June 2026 Draft Environmental Impact Report, construction would run about three years, from roughly July 2028 to August 2031.
The project will reach well beyond the reservoir site. Here's what the City's FAQ and the Draft EIR describe:
- Trucks. Construction traffic "will likely be along Dolores Drive due to safety reasons." The detailed traffic plan hasn't been written yet. For the excavation phase, the Draft EIR estimates about 9,230 two-way truck trips, or 100 to 110 a day, on routes that can't avoid residential streets. The EIR calls these conservative estimates and expects them to drop during design.
- Pipelines. Water mains would be replaced or relocated in La Coronilla Drive, Dolores Drive, Ricardo Avenue, La Vista del Oceano and Meigs Road.
- Hours. Most work would run 7 a.m. to 5 p.m., Monday through Friday. Some reservoir and large-pipeline work would happen outside those hours, with notice to neighbors in advance.
- Parking. Temporary street parking restrictions will be posted with signs, and the City says they "are not anticipated to begin until 2028."
- Noise and vibration. Demolition and tank construction will exceed 65 dBA, the top of the range the City's General Plan treats as normally acceptable for residential outdoor areas. The City proposes sound walls and noise-dampening devices. The Draft EIR requires low-vibration equipment within 25 feet of homes.
- Monitoring. Digging near Meigs Road and Dolores Drive requires archaeological and Chumash tribal monitors on site.
The Mesa Tree has a date too
The neighborhood conversation about Vic Trace so far has centered on trees, not trucks. The City's plan removes 55 of the 108 trees on the site and plants 75 native replacements. The Parks and Recreation Commission approved that plan unanimously on February 25, conditional on final approval of the project. Among the trees slated for removal is an old stone pine that Alta Mesa neighbors call the "Mesa Tree." A resident spoke at the commission meeting.
"Unfortunately in order to accomplish this water infrastructure project we have to remove some but we protected many and the hope is that this project will last 100 years and that we are improving the habitat on site when the project is over." Kelly Bourque, Senior Project Manager, speaking to KEYT
KEYT reported that the replacements are mostly red ironbark, hollyleaf cherry and blue elderberry, and that the City consulted the Ojai Raptor Center about wildlife on the site. KEYT also reported that no trees will be removed before construction begins. Based on the current schedule, the Mesa Tree has at least until 2028.
Where the open decisions sit on the calendar
The reservoir hasn't received final approval. The City's April 2026 road map lists Planning Commission consideration of the Final EIR and the Conditional Use Permit for December. According to the Civic Platform summary, the Draft EIR finds construction noise significant and unavoidable. That means approval requires the Planning Commission to state on the record that the project's benefits outweigh that impact. The public comment period on the Draft EIR closed July 30.
The next in-person update is sooner. The SB Mesa Neighborhood Association's Village Hall meets Thursday, October 15, from 6 to 7:30 p.m. at Free Methodist Church, 1435 Cliff Drive. Councilmember Mike Jordan will give a City Hall update. City Planner Michael Bedard is scheduled to cover when Vision Zero bids go out and where construction will start. Public Works will present the Vic Trace timeline and "what residents can expect during construction." Between meetings, you can reach the Vic Trace team at [email protected] or (805) 564-5579, and sign up for project emails at SantaBarbaraCA.gov/VicTrace.
If you're closer to La Coronilla, Dolores or Ricardo and thinking about what the coming years mean for your own plans, timing questions can be talked through calmly and early. Deborah Samuel follows these Mesa project dates closely and can walk you through how they fit your timeline, whether you're staying put or starting to think about a move. Get your instant home valuation & downsizing plan.